My Job in Leighton  

 

Main     Leighton job in HK (1)    (2)    (3)    (4)

 

H2604-澳門永利皇宮(2013)  H2504-西貢國際學校(2013)  H2448-荔枝角雨水龍(2008)  H2338-澳門新濠天地(2007)  

H2189-中環填海三期(2003)  H2028-天水圍輕鐵線(2002)  H2038-機場新停機坪(2001)  H2018-將軍澳地鐵站(2000)     

H2038-慈愛四期居屋(1999)  H1688-粉嶺康和居屋(1998)  H1899-机場德航大樓(1997)  H997 - 狗虱灣火藥庫(1995)  

H977 - 會展中心填海(1994)  H1368-西九龍填海區(1993)  H899 - 昂船洲鋪水管(1991)  H579 - 東區走廊三期(1988)

旅遊中國香港非洲美洲澳亞歐美旅詩趣詩禮頓同事朋友居所港昔

網主文教家人教會金句臺大同學花卉世最3  D

 

禮頓工作二十多年時,有所感而寫

  

滿

 

 

某年的 Annual Diner,承蒙 Jimmy Chu 之邀,寫了這對聯 :

義常存年年在

有英才歲歲來

 

 

 

 

 

 

 

中環填海三期地盆

   

                                                                     

 

 

 

 

 

揮手拂袖禮頓門,1988年7月加入,2016年3月離開禮頓,服務 27 年。

 

 

 

 

 

離開永利皇宫有感而寫 : 今日出宮;永不回頭

 

 

 

 

 

九年九年復九年;在禮頓服務了 27 年。

 

半生蹉跎與營役,往事瀝瀝在目前。

 

 

 

 

 

回顧半生在地盆工作,半生勞累追風月,為人解憂與解愁。

 

 

 

 

 

離開禮顿了,寄望後浪仍能高唱前浪美好之歌。

 

 

 

 

青春何逝?勞碌俗世,但求隨風,以天地為家。

 

 

當返工有如開鏡做戲之時,就想熄機說聲:" Sorry, I will be out"

 

 

在澳門永利地盆工作,每週匆匆來回港澳兩地。

 

 

習總到訪,放假三天,澳門真好。

 

 

永利地盆趕工,取消短周 . . . . . .

 

每次從香港乘船過澳门時都有風高路急孤身客之感

 

 

Warning warning and warning . . . . . 一個大笑話

 

 

暫别永利皇宮裙樓 . . . . . 調往裝修组

 

 

鬼佬老細 . . . . . . 每日出絕招 . . . . . . Go go go . . . . Go go go

 

 

懷念勞勞碌碌兩地忙的那段日子

 

 

永利地盆高層講D野真係信唔過架

 

 

My jobs in Civil/Building Engineering

 

From

To

 

Position Title

Description of Project / Work

Details of Highway construction, improvement and pavement reconstruction

           

06/2013

03/2016

Retired

LCAL

Macau

Site agent

Wynne Palace, Macau

Basement Construction and

Ffit-out work of Back of House

03/2013

06/2013

LCAL

Sai Kung

 

Site agent

Sai Kung International School

External Drainage work

12/2008

03/2013

LCAL

Lai Chi Kwok

 

Site agent

Lai Chi Kwok Transfer Scheme

Outfall construction

08/2007

12/2008

LCAL

Macau

Sub agent

City of Dreams, Macau

Construction of a 502,000 sqm luxury resort casino complex comprising 5 high towers and a 3 storey podium. Hotels: Hard Rock (46,850m2, 24 floors, 366 rooms), Grand Hyatt (52,850m2, 30 floors, 350 rooms), Hyatt Regency (80,660 m2 26 floors, 660 rooms), Crown (72,930m2, 31 floors, 295 rooms), Apartment Hotel (136,475m2, 37 floors, 861 rooms), Dragon Theatre (23,3743m2), podium for casino/retail and food and beverage 187,740m2.

 

External and Landscaping Works of Hotels, including drainage and pavement construction

04/2003

08/2007

LCAL

Central

Sub agent

Central Reclamation Phase III - Engineering Works

Reclamation of 18 hectares of land, construction of seawalls, ferry piers, a railway overrun tunnel, a dual three-lane road tunnel, a heliport, cooling water pumping stations and pipelines, roads and drainage and various M&E works.

 

Site formation and construct the associated road and drainage works, including the extension of a 4 cell box culvert to the new seafront

02/2001

04/2003

LCAL

Tin Shui Wai

Sub agent

KCRC Contract CC-230, Light Rail Civil, Permanent Way, Traction Power and Overhead Line

Light rail civil and systems works for interchange stations, Tin Shui Wai Phase 4 and Tin Shiu Wai reserve zone extension,  Light Rail grade separations at Pui To Road, junction LT1 and junction L,  modifications to the existing system.

 

Diversion and re-construction of existing road and modification of existing drainage and sewage system to allow the construction of new Light Rail

10/2000

02/2001

LCAL

Airport

 

Sub agent

Airport cargo port & runway phase 2

Drainage works and runway construction

04/1999

10/2000

LCAL

Tseung Kwan O

Sub agent

Tseung Kwan O Extension - MTRCL 607 Tseung Kwan O Station and Tunnels

Construction of an underground station, two cut and cover tunnels, a public transport interchange and associated substructures, as well as roadworks adjacent to the station. (project size: 20,000 m2)

 

Tunnel structures and road works adjacent to the station

03/1998

04/1999

LCAL

Tsz Oi

Sub agent

Redevelopment of Tsz Oi Estate Phase 4

Construction of six 41-storey residential blocks, comprising 1,920 flats, carpark, kindergarten, footbridges (including foundations) and external works. (GFA 185,000 m2)

 

All external works including the road, drainage and sewage system connected to the existing system

03/1997

04/1998

LCAL

Fan Ling

 

Sub agent

Fan Ling Estate

All external works including the road, drainage and sewage system connected to the existing system

 

02/1996

03/1997

LCAL

Airport

Sub agent

LSG Catering Facility at Chek Lap Kok

Design and construction of a 20,500 m2, 3-level facility incorporating production and returns areas, storage, administration and maintenance facilities and procurement management of all specialist equipment

 

All external works including the road, drainage and sewage system tied in to the main road and drainage system

07/1995

02/1996

LCAL

Kau Shat Wan

Sub agent

Explosives' Complex - Stage 1 Civil Works

Construction of access tunnels and ten caverns by drill and blast, reinforced-concrete cavern structures, blast walls, portal formation, dredging, reclamation, seawalls and site formation at Kau Shat Wan, Lantau Island.

 

Site formation, road and drainage works

07/1994

06/1995

LCAL

Waichai

Sub agent

Wanchai Reclamation Phase 1 Reclamation & West Bridge

Dredging, reclamation, seawalls, bridge, pumphouses and H-pile foundations for the extension to the Hong Kong Convention and Exhibition Centre.

 

Tie in road and drainage works to existing system

03/1992

06/1994

LCAL

 

Senior engineer

West Kowloon Reclamation Northern Area - Phase II

Reclamation of 100 hectares involving dredging of 4.2 million m3, deposition of 20 million m3 of sand fill, 1.4 km of seawall, drainage, demolition, roadworks, foundations and pipelines.

 

Seawall construction and temporary site access road

06/1990

02/1992

LCAL

Cheung Sha Wan

 

Senior engineer

North-west Kowloon sewage treatment and disposal project. Project involved 2,000 mm steel sewage pipes laying and pump station access chamber structure.

 

Laying 2000mm diameter MS underground pipe and construct road and pavement

07/1988

05/1990

LCAL

Sha Kei Wan

 

Senior engineer

Flyover and subways for Hong Kong Island eastern corridor phase 3. Project involved flyover, subway structure, footbridge, slope protection works.

Construction of flyover and subway structures for Hong Kong Island Eastern Corridor from Sha Kei Wan to Chai Wan

 

07/1987

06/1988

Slipform

PRC

 

Section engineer

Construction of Guangzhou Shenzhen – Zhuhai super highway

Road and drainage construction from Guangzhou to Shenzhen

 

04/1986

06/1987

Tai Fat

Sang Kee

TaiPo

 

Site agent

Slope improvement and road and bridge construction for phase 2 of Tai Po Road Improvement. Project involved slope improvement, protection, soil nails, retaining walls, road and drainage reconstruction, footbridge and car park.

 

To modify Tai Po Road by re-construction of existing road and drainage, building new footbridge, car park and retaining wall

06/1981

03/1986

Kwan

Lee

Shatin

 

Site agent

Reclamation, seawall and road construction at Shatin. Project involved seawall construction, seawall block casting yard and box culvert structure

 

Road and drainage work, including box culvert construction

11/1978

05/1981

Maeda

Shatin

 

Quantity surveyor

Road and drainage work, subway construction and landscaping works in Shatin

In charge of all quantity surveying for road and drainage on site

 

09/1977

10/1978

UDL

Tuen Mun

Site engineer

Reclamation works, road and drainage work at Tuen Mun

In charge of a site laboratory, carrying out tests on site formation and concrete cubes test for concrete structure